The electrolysis equipment to be installed in Harjavalta consists of four roughly 10-meter-long and about 100-ton stacks, each of which produces green hydrogen at a capacity of 5 MW. Together, the four stacks have 20 MW of capacity.
“In terms of hydrogen production, the electrolysis equipment is the most critical piece of technology. Its arrival in Harjavalta is a significant step towards green hydrogen production. The intensive and smooth 18-month cooperation with Sunfire has now materialized as the delivery of the first electrolyzer stacks,” said Herkko Plit, CEO of P2X Solutions.
The construction of P2X Solutions’ green hydrogen production plant began with excavation work in the summer of 2022, and the buildings reached their rooftop height in the beginning of June 2023. During the fall of 2023 and winter of 2024, approximately one hundred employees will be working at the construction site on equipment, piping and electrical work, among other things.